Utility / owner / operatorWAInvestor-owned utilityHow EIA classifies an organization, such as a public utility, cooperative or investor-owned company.Definition ↗
Operated nameplate capacity, operating generatorsFull nameplate MW of operating generators at plants this organization runs, including shares held by other owners.Definition ↗
2,590.8MW
Source & method
Sum of operating generator nameplate MW at plants where this organization is the reported operator
2024 inventory · reported · derived · valid · final
19 of 19 plants included.
Reported operating capacity; partial plant/unit coverage is marked
Owned nameplate capacity, operating generatorsOperating generator nameplate MW multiplied by this organization’s ownership share, once per generator. This can include plants another organization operates.Definition ↗
3,161.3MW
Source & method
Sum over operating generators of nameplate MW x this organization's ownership fraction (reported schedule or EIA-860 schedule-4 default)
2024 inventory · reported · derived · valid · final
Example: an operating 100 MW generator with a 25% ownership share contributes 25 MW to owned capacity. Its operator counts the full 100 MW. Neither quantity establishes who buys its electricity.
Operates
Operating MWFull operating nameplate capacity at plants this organization runs, including shares held by other owners.Definition ↗
Share-weighted MWAn organization with a reported share of a generator. Owned MW applies that share to operating nameplate capacity; it does not establish who buys the output.Definition ↗
Through BPA: 2.6% of sales; unspecified purchases: 0.3%. Filed as claimant “Puget Sound Energy”with separate product rows (Puget Sound Energy Green Direct Program).
By report year MWh and shares of Washington retail sales including losses; not generation, not a compliance finding
Each year as Commerce's fuel-mix system holds it: MWh and shares of the utility's Washington retail sales including line losses, never generation and never a compliance finding. Years before CY2018 are Commerce's restatement under the 2019 method, not the disclosure published for the year; no change is taken across that break.
Disclosed supply by report year
Report year
Washington retail sales · MWh
Mix · share of Washington sales
Through BPA · share
Unspecified · share
CY2018 onUnspecified power is disclosed as its own category, as the statute has required since ESHB 1428 (2019); Commerce's statutory aggregate carries an unspecified row from CY2018. CY2022-Aggregate Fuel Mix Time Series.xlsx ↗ (Info!A10; Info!A16)
CY2024
20,666,437 MWh
Natural Gas 32.0% · Hydro 28.3% · Wind 19.8%
2.6%
0.3%
CY2023
20,805,133 MWh
Natural Gas 29.9% · Hydro 29.6% · Wind 21.6%
1.7%
0.2%
CY2022
22,629,715 MWh
Hydro 26.5% · Coal 23.1% · Natural Gas 23.0%
3.2%
9.8%
CY2021
22,147,657 MWh
Natural Gas 30.5% · Coal 24.5% · Hydro 24.0%
4.3%
9.2%
CY2020
21,706,876 MWh
Natural Gas 27.0% · Hydro 24.1% · Coal 23.0%
1.7%
14.1%
CY2019
22,139,390 MWh
Coal 32.0% · Natural Gas 27.9% · Hydro 17.2%
2.4%
13.3%
CY2018
22,233,671 MWh
Coal 31.2% · Hydro 22.3% · Market 19.6%
3.4%
19.6%
Before CY2018: restatedCommerce's current system run over what utilities reported for a year before CY2018. The disclosure published for that year followed the old law, which required Commerce to assign fuel shares to unspecified power; this run keeps unspecified power as its own Market category, and Commerce's statewide totals for these years differ from the statutory reports. Not the label customers received, and not comparable with CY2018 on. CY2022-Aggregate Fuel Mix Time Series.xlsx ↗ (Info!A10; Info!A16)
Categories and shares as Commerce computed them from declared resources, the BPA system mix (BPA's own mix applied to BPA deliveries, remainder unspecified) and unspecified purchases; a declared resource needs ownership or an auditable contract and its REC; renewable power without the REC counts as unspecified. Not an emissions accounting.
Carbon allowances · no-cost allocationAn emissions allowance Washington assigns to an eligible utility without charge. It is not measured emissions.Definition ↗
Cap-and-investWashington’s program that limits covered greenhouse gas emissions and requires allowances for them.Definition ↗ period 1 · t CO2e
No-cost carbon allowances
6,642,604t CO2e
2023 calendar year
Source & method
Ecology's Electric Utility Allowance Allocation Schedule under WAC 173-446-230: allowances allocated at no cost to a CETA-obligated electric utility for the calendar year, one allowance = one metric ton of CO2 equivalent. An allocation computed from Ecology's forecast of the utility's Washington retail load and resource supply, not measured emissions and not a cap on the utility
2023 calendar year · reported · direct · valid · final
Ecology's Electric Utility Allowance Allocation Schedule under WAC 173-446-230: allowances allocated at no cost to a CETA-obligated electric utility for the calendar year, one allowance = one metric ton of CO2 equivalent. An allocation computed from Ecology's forecast of the utility's Washington retail load and resource supply, not measured emissions and not a cap on the utility
2024 calendar year · reported · direct · valid · final
Ecology's Electric Utility Allowance Allocation Schedule under WAC 173-446-230: allowances allocated at no cost to a CETA-obligated electric utility for the calendar year, one allowance = one metric ton of CO2 equivalent. An allocation computed from Ecology's forecast of the utility's Washington retail load and resource supply, not measured emissions and not a cap on the utility
2025 calendar year · reported · direct · valid · final
Ecology's Electric Utility Allowance Allocation Schedule under WAC 173-446-230: allowances allocated at no cost to a CETA-obligated electric utility for the calendar year, one allowance = one metric ton of CO2 equivalent. An allocation computed from Ecology's forecast of the utility's Washington retail load and resource supply, not measured emissions and not a cap on the utility
2026 calendar year · reported · direct · valid · final
The utility's no-cost allocation for the year multiplied by the settlement price of the most recent quarterly Cap-and-Invest auction. An illustration of scale, not revenue received: a utility consigns only part of its allocation, the price changes every quarter, and the proceeds of any sale must go back to customers
2026 calendar year · reported · derived · valid · final
2026 allocation at the $39.50 settlement price of auction #15 on 2026-09-02
At the settlement price of $39.50 per allowance from auction #15 on 2026-09-02 (Ecology’s summary report ↗), where 3,484,205 allowances were sold on behalf of consigning entities statewide. What the allocation would fetch at one auction's price. Utilities consign part of their allowances to these auctions and must return the proceeds to customers; the rest they hold for compliance or bank.
Allocated to “Puget Sound Energy” on Ecology’s schedule, filed as investor-owned utility. A utility cannot sell these allowances to another company: it uses them for compliance, banks them, transfers them to an eligible generator, or consigns them to a quarterly auction, and the proceeds must go back to customers.
How Ecology computed each year
Year
Forecast WA load (MWh)
Forecast supply
Allowances (t CO2e)
Forecast filed in
2023
22,985,346MWh
Natural gas 37.6% · Renewable or non-emitting 50.6% · Coal 11.8%
Supply shares are Ecology’s forecast for the allocation, taken from the utility’s own filing. They are not the disclosed fuel mix above, which reports what was actually sold.
An allocation of allowances, not a measurement of emissions and not a cap on the utility. Ecology computes it from its forecast of the utility's Washington retail load and resource supply, and reissues the schedule as forecasts and the BPA emission factor change; the supply shares here are that forecast, not the disclosed fuel mix.
Money · FERC Form 1The annual financial report large investor-owned utilities file with the federal energy regulator.Definition ↗
2025 · USD nominal
Purchased power, settlements
1,165,290,255USD
2025
Partial or uncertain coverage: 95 named sellers; 3 adjustment and 2 market-settlement rows and the filing total row excluded
Source & method
FERC Form 1 Schedule 326 total settlement over named sellers (adjustment rows excluded), nominal dollars for the report year
2025 calendar year · reported · derived · suspect · final
117 of 119 native rows included.
95 named sellers; 3 adjustment and 2 market-settlement rows and the filing total row excluded
Purchased power by seller Financial relationshipA documented financial relationship between named parties, with an amount where public and its reported or calculated basis.Definition ↗
Schedule 326 settlements for 2025, largest first(top 60 of 95). Seller names as filed; a link means a reviewed match to an organization in this atlas.
california iso - eim purchasesOS · market operator, not a bilateral seller
26,275,860 USD
california isoOS · market operator, not a bilateral seller
3,049,956 USD
Adjustment rows filed on the same schedule (3)
ca carbon obligationAD · a mechanism, not a party
419,074 USD
residential exchangeAD · a mechanism, not a party
-82,212,871 USD
washington emission allowanceAD · a mechanism, not a party
95,458,798 USD
Missing cells stay missing; partial seller sums are marked and have no USD/MWh ratio. FERC Form 1 Schedule 326 rows for the report year; seller names as filed; an organization link exists only through a reviewed crosswalk row; MWh uses purchased_mwh through 2020 and purchased other than storage from 2021. A row counts as a seller when it names a party, whatever its purchase type: FERC's AD code marks an adjusting entry, and an adjusting entry naming a company is still money between that company and the respondent. Rows whose name is a mechanism (deferrals, allowances, the residential exchange) are listed as adjustments; rows naming a market operator are listed as market settlements
Revenue by customer class
Class
USD
MWh
USD/MWh
Customers (avg/month)
residential sales
1,944,566,138USD
11,434,185MWh
170.07 USD/MWh
1,104,338customers (monthly average)
small or commercial
1,352,174,424USD
8,649,567MWh
156.33 USD/MWh
135,533customers (monthly average)
large or industrial
151,263,982USD
1,040,902MWh
145.32 USD/MWh
3,158customers (monthly average)
public street and highway lighting
25,686,397USD
69,979MWh
367.06 USD/MWh
8,414customers (monthly average)
sales for resale
375,516,235USD
9,500,294MWh
39.53 USD/MWh
9customers (monthly average)
Schedule 300 class lines as the form computes them (as_computed); usd_per_mwh is revenue over MWh sold for that class; the class lines are not re-summed here; EIA-861 revenue and price for the same utility are on the retail block and can differ (different survey, scope and year)
Operation and maintenance expenses
Total electric O&Mas the form computes it
2,581,537,393 USD
Power productionas the form computes it
1,686,866,353 USD
of which purchased power (account 555)reported line· account 555
1,208,281,072 USD
of which fuel, steam generation (501)reported line· account 501
56,862,104 USD
of which fuel, other generation (547)reported line· account 547
275,829,197 USD
Transmissionas the form computes it
226,702,410 USD
Distributionas the form computes it
136,858,691 USD
Customer accountsas the form computes it
68,451,478 USD
Customer service and informationas the form computes it
265,798,532 USD
Salesas the form computes it
1,188,192 USD
Administrative and general, operationas the form computes it
176,533,111 USD
Administrative and general, maintenanceas the form computes it· account 935
19,138,626 USD
of which transmission by others (565)reported line· account 565
196,912,868 USD
Schedule 320 electric operation and maintenance: function totals as the form computes them (as_computed) with the purchased power, fuel and wheeling accounts listed beneath as components, never added again
Nominal dollars for the report year as filed; revisions arrive for months after the April deadline; the pinned PUDL release fixes the snapshot FERC respondent 162· XBRL entity C000171; link basis: pudl_assn_1to1.
Retail electricity sold
Full serviceA utility that sells electricity to customers. Full-service sales include both electricity and delivery.Definition ↗
Average revenue per kWhRevenue divided by electricity sold. This average is not a tariff or a household bill.Definition ↗ is realized revenue ÷ sales, not a tariff.
WA · commercial
Retail sales
8,625,073MWh
2024
Source & method
EIA-861 electricity sold to ultimate customers for the stated utility, state, customer class and service type; calendar year
2024 calendar year · reported · direct · valid · final
Sold to retail customers in the stated state (utility x state grain); bundled full-service rows only in the summaries; energy-only and delivery-only rows are listed but never added to bundled sales. Realized average revenue per kWh is not a tariff.
Clean-energy obligationsFive separate records of a clean-energy obligation, never merged: applicability (which statute reaches this utility and why), target (the figure as enacted or ordered, or as a filing or compilation restates it, with that standing marked), filed achievement (what the utility itself reported for a period), determination (what the issuing body decided about the filing, with its order number and date) and deciding event (the open proceeding, its next step and where to comment). A fuel-mix value is none of these, and a filing that restates a target does not enact it.Definition ↗
checked 2026-09-27
Five kinds kept apart: what applies, what is owed, what the utility filed, what the issuing body decided, and the open proceeding. The disclosed-supply block above is the same utility's fuel mix as Commerce computed it; read it beside these rows, never as a verdict on them. Rows checked through 2026-09-27; a row past its review date is marked, not removed.
Clean Energy Transformation Act RCW 19.405 ↗ · Washington Utilities and Transportation Commission
Applies because investor-owned electric utility subject to the Clean Energy Transformation Act; files its clean energy implementation plan with the commission(19.405.020(14) and (23); 19.405.060(1)(a)), effective 2019-05-07. Statute ↗
Clean energy implementation plan every four years (RCW 19.405.060) with interim targets; coal out of the allocation by 2025-12-31, greenhouse gas neutral retail sales from 2030-01-01, 100 percent renewable or nonemitting by 2045-01-01
What is owed The obligation as enacted or ordered; a utility’s own restatement does not enact it.
interim target for the 2022-2025 compliance periodfiled Puget Sound Energy · docket UE-210795 · PSE 2023 Biennial Clean Energy Implementation Plan Update · Chapter One, section 2 (Meeting our clean energy obligations)· of retail electric load As the document puts itPSE maintains an interim target to serve at least 54.5 percent of retail electric load with clean energy resources over the 2022-2025 compliance period; the interim target is the average of the annual goals. The UTC denied PSE's petition to cut the 2024 and 2025 interim targets to 48 percent a year on 2024-11-07 and the docket closed 2024-11-08. PSE's own expression of the period target as a four-year average; the commission's approved interim targets are the annual series 43, 53, 59 and 63 percent (Final Order 08; Order 12 condition (1)(a)-(b)), which the compliance report of 2026-07-01 also restates. A utility's restatement does not replace the ordered figures.
annual interim target approved by the commissionordered Washington Utilities and Transportation Commission · docket UE-210795 · Order 12 Approving CEIP Biennial Update Subject to Conditions · condition (1)(a); interim targets first approved in Final Order 08 paragraph 48· of retail load served by renewable and nonemitting electric generation As the document puts it"PSE will maintain the Interim Targets approved by the Commission in Order 08 of Docket UE-210795 for the remainder of this compliance period (i.e., 2022 - 43 percent of retail load served by renewable and nonemitting electric generation; 2023 - 53 percent; 2024 - 59 percent; 2025 - 63 percent)". Condition (1)(b) keeps one interim target per year; (1)(c) says unreasonably costly energy needed for 2025 will be considered at the compliance review.
annual interim target approved by the commissionordered Washington Utilities and Transportation Commission · docket UE-210795 · Order 12 Approving CEIP Biennial Update Subject to Conditions · condition (1)(a); interim targets first approved in Final Order 08 paragraph 48· of retail load served by renewable and nonemitting electric generation As the document puts it"PSE will maintain the Interim Targets approved by the Commission in Order 08 of Docket UE-210795 for the remainder of this compliance period (i.e., 2022 - 43 percent of retail load served by renewable and nonemitting electric generation; 2023 - 53 percent; 2024 - 59 percent; 2025 - 63 percent)". Condition (1)(b) keeps one interim target per year; (1)(c) says unreasonably costly energy needed for 2025 will be considered at the compliance review.
annual interim target approved by the commissionordered Washington Utilities and Transportation Commission · docket UE-210795 · Order 12 Approving CEIP Biennial Update Subject to Conditions · condition (1)(a); interim targets first approved in Final Order 08 paragraph 48· of retail load served by renewable and nonemitting electric generation As the document puts it"PSE will maintain the Interim Targets approved by the Commission in Order 08 of Docket UE-210795 for the remainder of this compliance period (i.e., 2022 - 43 percent of retail load served by renewable and nonemitting electric generation; 2023 - 53 percent; 2024 - 59 percent; 2025 - 63 percent)". Condition (1)(b) keeps one interim target per year; (1)(c) says unreasonably costly energy needed for 2025 will be considered at the compliance review.
petition to lower the 2024 and 2025 annual interim targetsproposed Puget Sound Energy · docket UE-210795 · Petition to amend Orders 08 and 12 (2024-09-27), as described in Order 14 · Order 14 paragraphs 3 and 18(1)· of retail load served by renewable and nonemitting electric generation As the document puts itDenied. Order 14 (2024-11-08): "Puget Sound Energy's Petition filed September 27, 2024, is denied"; the petition asked to lower the targets "to 48 percent" and asserted that without approval PSE would need "a projected $200 million in short-term clean energy resources".
eliminate coal-fired resources from the utility's allocation of electricityenacted Washington State Legislature · RCW 19.405.030 Coal-fired resources - Depreciation schedule - Penalties· of the utility's allocation of electricity supplied by coal-fired resources As the document puts itOn or before December 31, 2025. Excludes decommissioning and remediation costs; long-term BPA purchases are exempt unless the electricity is known to be coal-fired. The commission must set depreciation schedules ending no later than 2025-12-31.
annual clean energy goal for 2025proposed Puget Sound Energy · docket UE-210795 · PSE 2023 Biennial Clean Energy Implementation Plan Update · Chapter One, section 2 (Meeting our clean energy obligations)· of retail electric load As the document puts itPSE sought to adjust the 2025 annual goal from 63 percent to 60 percent while keeping the 54.5 percent four-year interim target, citing supply constraints and a tightening market for clean energy resources. Not adopted: Order 12 (2024-03-25) condition (1)(a) kept the 2025 interim target at 63 percent.
annual interim target approved by the commissionordered Washington Utilities and Transportation Commission · docket UE-210795 · Order 12 Approving CEIP Biennial Update Subject to Conditions · condition (1)(a); interim targets first approved in Final Order 08 paragraph 48· of retail load served by renewable and nonemitting electric generation As the document puts it"PSE will maintain the Interim Targets approved by the Commission in Order 08 of Docket UE-210795 for the remainder of this compliance period (i.e., 2022 - 43 percent of retail load served by renewable and nonemitting electric generation; 2023 - 53 percent; 2024 - 59 percent; 2025 - 63 percent)". Condition (1)(b) keeps one interim target per year; (1)(c) says unreasonably costly energy needed for 2025 will be considered at the compliance review.
Not yet curated Washington Utilities and Transportation Commission · docket UE-210795 · Order 13 Granting Petition to Amend Orders 8 and 12 · paragraph 10 As the document puts itNo 2026-2029 interim targets exist for PSE. Order 13: "PSE is no longer required to file a 2025 CEIP, subject to the conditions described in Dockets UG-240434 and UE-240433"; the clean energy implementation plan, integrated resource plans and public participation plan are consolidated into "a single Integrated System Plan, to be filed in 2027 pursuant to the outcome of Docket U-240281" (ESHB 1589). The policy research of 2026-09-18 recorded the 2025 CEIP docket as not found; this order is why. Not available: not yet filed
greenhouse gas neutral retail sales, at least 80 percent from renewable and nonemitting resourcesenacted Washington State Legislature · RCW 19.405.040 Greenhouse gas neutral electricity supply· of retail sales of electricity to Washington retail electric customers As the document puts itBy January 1, 2030. Up to 20 percent of the obligation may be met by alternative compliance: alternative compliance payments, unbundled renewable energy credits or energy transformation projects. Four-year compliance periods 2030-2033, 2034-2037, 2038-2041 and 2042-2044.
nonemitting generation and renewable resources supply 100 percent of retail salesenacted Washington State Legislature · RCW 19.405.050 One hundred percent renewable and nonemitting electricity supply· of retail sales of electricity to Washington retail electric customers As the document puts itBy January 1, 2045, with an annual demonstration of compliance after that date.
What the utility filed Its own report of what it did; a number it reports, not a verdict.
electricity supplied from renewable and nonemitting resources over the implementation period, as reported by the utilityfiled Puget Sound Energy · docket UE-210795 · 2026 Clean Energy Compliance Report for the 2022-2025 implementation period (filed 2026-07-01; substituted 2026-07-06) · Section 2, paragraph before Table 4; Table 5· CETA-eligible energy, 2022-2025 sum As the document puts it"From 2022-2025, PSE supplied 40,185,529 MWh from renewable and nonemitting resources, which exceeds the 40,070,388 MWh PSE projected would be necessary to achieve the interim target." Load grew faster than forecast, so the MWh exceeded the plan while the share did not.
share of retail electric load served with clean energy, as reported by the utilityfiled Puget Sound Energy · docket UE-210795 · 2026 Clean Energy Compliance Report for the 2022-2025 implementation period (filed 2026-07-01; substituted 2026-07-06) · Section 2, Table 6 (Comparison of retail sales, energy, and percentage), row Actual· CETA-eligible energy divided by CETA retail load (retail sales less load reduction) As the document puts itTable 6 column "CETA percentage (CETA-eligible energy / CETA retail load)". Table 3 prints 44.3% for 2022 with a footnote; Table 6 is used here.
share of retail electric load served with clean energy, four-year average, as reported by the utilityfiled Puget Sound Energy · docket UE-210795 · 2026 Clean Energy Compliance Report for the 2022-2025 implementation period (filed 2026-07-01; substituted 2026-07-06) · Section 2 Interim targets, Table 3 and closing paragraph· CETA-eligible energy divided by CETA retail load (retail sales less load reduction), 2022-2025 average As the document puts it"PSE served an average of 50.6% of retail electric load with clean energy"; "PSE's actual four-year average of 50.6% clean and nonemitting energy was less than the four-year interim target of 54.5%", and PSE "concludes that its actions during the implementation period reflect reasonable and sufficient progress". The report also states the incremental cost "slightly exceeded the 2% incremental cost threshold per WAC 480-100-660". The utility's own account; the commission has not yet decided on it. Copy on PSE's library: https://www.cleanenergyplan.pse.com/library
share of retail electric load served with clean energy, as reported by the utilityfiled Puget Sound Energy · docket UE-210795 · 2026 Clean Energy Compliance Report for the 2022-2025 implementation period (filed 2026-07-01; substituted 2026-07-06) · Section 2, Table 6 (Comparison of retail sales, energy, and percentage), row Actual· CETA-eligible energy divided by CETA retail load (retail sales less load reduction) As the document puts itTable 6 column "CETA percentage (CETA-eligible energy / CETA retail load)".
share of retail electric load served with clean energy, as reported by the utilityfiled Puget Sound Energy · docket UE-210795 · 2026 Clean Energy Compliance Report for the 2022-2025 implementation period (filed 2026-07-01; substituted 2026-07-06) · Section 2, Table 6 (Comparison of retail sales, energy, and percentage), row Actual· CETA-eligible energy divided by CETA retail load (retail sales less load reduction) As the document puts itTable 6 column "CETA percentage (CETA-eligible energy / CETA retail load)".
share of retail electric load served with clean energy, as reported by the utilityfiled Puget Sound Energy · docket UE-210795 · 2026 Clean Energy Compliance Report for the 2022-2025 implementation period (filed 2026-07-01; substituted 2026-07-06) · Section 2, Table 6 (Comparison of retail sales, energy, and percentage), row Actual· CETA-eligible energy divided by CETA retail load (retail sales less load reduction) As the document puts itTable 6 column "CETA percentage (CETA-eligible energy / CETA retail load)".
What the issuing body decided Orders and acknowledgments on the filings.
final order approving the 2021 clean energy implementation plan subject to conditionsordered Washington Utilities and Transportation Commission · docket UE-210795 · Final Order 08 Approving Clean Energy Implementation Plan Subject to Conditions · paragraphs 48 and 54 As the document puts it"We approve the Company's Interim Targets subject to conditions recommended by Public Counsel. As required by RCW 19.405.060(1)(a)(ii) and WAC 480-100-640(2)(a)(i), PSE's Interim Targets demonstrate how the Company will make reasonable progress towards CETA's clean energy requirements." Effective 2023-06-06 (entered 2023-06-05; conditions in Appendix A).
order approving the 2023 biennial CEIP update subject to conditions, keeping the annual interim targetsordered Washington Utilities and Transportation Commission · docket UE-210795 · Order 12 Approving CEIP Biennial Update Subject to Conditions · conditions (1)(a)-(c), (2), (3) As the document puts itApproved at the recessed open meeting of 2024-03-22; effective 2024-03-25. PSE "requested that the Commission clarify whether the Interim Targets may be expressed as a four-year average" and asked to lower 2025 from 63 to 60 percent; condition (1) kept the annual series.
order amending Orders 08 and 12: PSE no longer required to file a 2025 CEIP; planning consolidated into a 2027 Integrated System Planordered Washington Utilities and Transportation Commission · docket UE-210795 · Order 13 Granting Petition to Amend Orders 8 and 12 · paragraphs 4 and 10 As the document puts it"PSE is no longer required to file a 2025 CEIP, subject to the conditions described in Dockets UG-240434 and UE-240433"; granted "subject to the condition that PSE fulfill the commitments it made in its June 27, 2024, filing". Basis: ESHB 1589.
order denying the petition to lower the 2024 and 2025 interim targets to 48 percentordered Washington Utilities and Transportation Commission · docket UE-210795 · Order 14 Denying Petition to Amend Orders 8 and 12 · paragraph 18(1) As the document puts itOpen meeting 2024-11-07 (2:1); effective 2024-11-08. The order keeps the targets while saying "rote adherence to interim targets is not anticipated" and that the compliance review will consider the circumstances.
Not yet curated Washington Utilities and Transportation Commission · docket UE-210795 · Docket UE-210795 orders list · latest order is Order 14 of 2024-11-08 As the document puts itNo order on the compliance report as of 2026-09-21. The commission opened written comments (due 2026-10-20) and will decide whether PSE complied with its interim targets for the first implementation period; the report's 50.6 percent is the utility's figure, not a finding. Not available: not yet decided
The open proceeding Where the next decision is being made, and how to take part.
commission review of PSE's 2026 Clean Energy Compliance Report: written comments invitedopen Washington Utilities and Transportation Commission · docket UE-210795 · Notice of Opportunity to File Written Comments (Due By Tuesday, October 20, 2026, by 5:00 p.m.) · pages 1-2 As the document puts it"The Commission would like to hear from you to what extent PSE's Clean Energy Compliance Report demonstrates whether PSE has made progress towards the goals of its CEIP." Submit online (Consumer Protection web portal), by email to comments@utc.wa.gov, or by mail; cite Docket UE-210795. Comments are posted publicly.Next: written comments due to the commission by 5:00 p.m.by 2026-10-20· Take part ↗
No documented JSON API; the `apiproxy` host answered HTTP 500.30 all session and detail pages said "Record not found".The document endpoint served every filing read on 2026-09-19 and 2026-09-21; it remains undocumented.
resolved
Docket files before 2024 are not available. We are working to resolve the issue.
open
All PDF; targets need hand transcription.
open
WAC 480-100-600 through -665 (CEIP content, biennial updates -640(11), public participation -655): snapshot; WAC not fetched.
open
2025 CEIP docket not found by search (unverified).Order 13 in UE-210795 (2024-07-11): PSE is no longer required to file a 2025 CEIP; planning is consolidated into a 2027 Integrated System Plan.
resolved
Energy Independence Act (Initiative 937) RCW 19.285 ↗ · Washington Utilities and Transportation Commission
Applies because qualifying utility under the Energy Independence Act: an electric utility serving more than 25,000 customers in Washington((19)), effective 2006-11-07. Statute ↗
Biennial conservation acquisition target and an annual eligible-renewable target (15 percent of load from 2020) for utilities serving more than 25,000 Washington customers
What is owed The obligation as enacted or ordered; a utility’s own restatement does not enact it.
eligible renewable resources or renewable energy credits, or a combination, equal to at least 15 percent of load each year from 2020enacted Washington State Legislature · RCW 19.285.040 Energy conservation and renewable energy targets · (2)(a)(iii)· of the qualifying utility's load As the document puts it"At least 15 percent of its load by January 1, 2020, and each year thereafter" (2)(a)(iii), after 3 percent (2012-2015) and 9 percent (2016-2019). Initiative 937, approved 2006-11-07 (2007 c 1). Subsection (2) also provides alternative compliance paths (accelerated conservation and demand response; the four percent incremental-cost cap), so a utility can comply below 15 percent, as Clark Public Utilities does.
2024-2025 biennial conservation acquisition target accepted by the commissionordered Washington Utilities and Transportation Commission · docket UE-230892 · Order 01 Accepting 2024-2033 Ten-Year Achievable Conservation Potential and 2024-2025 Biennial Conservation Target, Subject to Conditions · findings (7)-(9) As the document puts it"PSE's calculation of its 2024-2025 biennial conservation target (EIA Target) of 304,400 MWh is consistent with RCW 19.285.040(1) and WAC 480-109-120(1)"; the same order accepts an EIA Penalty Threshold of 268,702 MWh and a ten-year potential of 1,521,999 MWh. Commerce's 2026 report summary carries 268,702 MWh as PSE's target: that is the penalty threshold, not the target.
2024-2025 EIA penalty threshold accepted by the commissionordered Washington Utilities and Transportation Commission · docket UE-230892 · Order 01 Accepting 2024-2033 Ten-Year Achievable Conservation Potential and 2024-2025 Biennial Conservation Target, Subject to Conditions · finding (9) As the document puts it"PSE's calculation of its 2024-2025 EIA Penalty Threshold of 268,702 MWh is consistent with" the rule. The threshold is the level below which RCW 19.285.060 penalties apply; the target is 304,400 MWh.
biennial conservation acquisition target for 2024-2025compiled Washington State Department of Commerce · EIA 2026 Report Summary and Detail.xlsx, sheet Conservation by Utility · cell B17· the commission's 2024-2025 EIA penalty threshold (UE-230892 Order 01), not its 304,400 MWh EIA target As the document puts itBiennium 2024-2025. Prior biennium 2022-2023 target 536717.135 MWh; change from the 2022-2023 target -0.49936.
2026-2027 biennial conservation acquisition target accepted by the commissionordered Washington Utilities and Transportation Commission · docket UE-250834 · Order 01 Accepting 2026-2035 Ten-Year Achievable Conservation Potential and 2026-2027 Biennial Conservation Target, Subject to Conditions · finding (7) As the document puts it"PSE's calculation of its 2026-2027 EIA target of 193,228 MWh is consistent with RCW 19.285.040(1) and WAC 480-109-120(1)"; the order also accepts a ten-year achievable potential of 966,140 MWh (2026-2035). Effective 2026-01-14.
2026-2027 EIA penalty threshold accepted by the commissionordered Washington Utilities and Transportation Commission · docket UE-250834 · Order 01 Accepting 2026-2035 Ten-Year Achievable Conservation Potential and 2026-2027 Biennial Conservation Target, Subject to Conditions · finding (9) As the document puts it"PSE's calculation of its 2026-2027 EIA penalty threshold of 156,781 MWh is consistent with" the rule; decoupling penalty threshold 9,661 MWh.
renewable energy target for 2026compiled Washington State Department of Commerce · EIA 2026 Report Summary and Detail.xlsx, sheet Renewable by Utility· of average load 2024-2025 As the document puts itAverage load 2024-2025 21178119 MWh.
What the utility filed Its own report of what it did; a number it reports, not a verdict.
verified electric conservation savings over the biennium, as reported by the utilityfiled Puget Sound Energy · docket UE-230892 · 2024-2025 Biennial Conservation Report for Electric and Natural Gas Programs · Executive Summary, Table 0-1· total verified conservation savings, all programs As the document puts itTable 0-1: total conservation savings 574,489 MWh against a 408,065 MWh goal; "Total Verified Penalty Threshold Savings" 519,873 MWh against the 283,922 MWh combined threshold (268,702 EIA plus 15,220 decoupling). Report filed 2026-06-01 under WAC 480-109-120(4).
verified penalty-liable conservation savings over the biennium, as reported by the utilityfiled Puget Sound Energy · docket UE-230892 · 2024-2025 Biennial Conservation Report for Electric and Natural Gas Programs · Executive Summary, Table 0-1; Section II.G· savings from programs that count toward the EIA and decoupling penalty thresholds As the document puts itExcess over the combined threshold: 235,951 MWh.
conservation acquired in 2024compiled Washington State Department of Commerce · EIA 2026 Report Summary and Detail.xlsx, sheet Conservation by Utility · cell C17 As the document puts itCounts toward the 2024-2025 biennial target.
2024-2025 conservation acquired as a share of retail load, as Commerce computed itcompiled Washington State Department of Commerce · EIA 2026 Report Summary and Detail.xlsx, sheet Conservation by Utility · cell G17· of retail load over the biennial period's two load years (Commerce's sheet Select Data) As the document puts itCommerce's column G formula, (2024 acquired + 2025 acquired) / the biennial period's two load years on sheet Select Data (columns C and D); the cell's value, not recomputed. Commerce formats it as a percent to one decimal.
total conservation savings as a share of the 2024-2025 target, as Commerce computed itcompiled Washington State Department of Commerce · EIA 2026 Report Summary and Detail.xlsx, sheet Conservation by Utility · cell F17· of the 2024-2025 conservation target in Commerce's column B As the document puts itCommerce's column F formula, (2024 acquired + 2025 acquired + excess from the prior two bienniums) / 2024-2025 target; the cell's value, not recomputed. Commerce formats it as a whole percent.
excess conservation carried from the prior two bienniums toward the 2024-2025 targetcompiled Washington State Department of Commerce · EIA 2026 Report Summary and Detail.xlsx, sheet Conservation by Utility · cell E17 As the document puts itCommerce's column E.
conservation acquired in 2025compiled Washington State Department of Commerce · EIA 2026 Report Summary and Detail.xlsx, sheet Conservation by Utility · cell D17 As the document puts itCounts toward the 2024-2025 biennial target.
qualifying renewable resources acquired for 2026compiled Washington State Department of Commerce · EIA 2026 Report Summary and Detail.xlsx, sheet Renewable by Utility As the document puts itEqual to 0.15 of average load 2024-2025; 2025 qualifying renewables were 3174553.2 MWh. Incremental cost of eligible renewables as a share of revenue requirement 0.007212.
What the issuing body decided Orders and acknowledgments on the filings.
order accepting the ten-year conservation potential and the 2024-2025 biennial conservation target, subject to conditionsordered Washington Utilities and Transportation Commission · docket UE-230892 · Order 01 Accepting 2024-2033 Ten-Year Achievable Conservation Potential and 2024-2025 Biennial Conservation Target, Subject to Conditions · findings (6)-(11) As the document puts itAccepts a ten-year achievable potential of 1,521,999 MWh, an EIA target of 304,400 MWh, an EIA penalty threshold of 268,702 MWh and a decoupling penalty threshold of 15,220 MWh. Effective 2024-01-17.
order accepting the 2026-2035 ten-year conservation potential and the 2026-2027 biennial conservation target, subject to conditionsordered Washington Utilities and Transportation Commission · docket UE-250834 · Order 01 Accepting 2026-2035 Ten-Year Achievable Conservation Potential and 2026-2027 Biennial Conservation Target, Subject to Conditions · findings (6)-(10) As the document puts itAccepts a ten-year achievable potential of 966,140 MWh, an EIA target of 193,228 MWh, an EIA penalty threshold of 156,781 MWh and a decoupling penalty threshold of 9,661 MWh, "pursuant to Order 7 in Docket UE-121697, subject to the conditions" of the order.
order accepting the 2024-2025 biennial conservation report: PSE in compliance with its biennial conservation targetsordered Washington Utilities and Transportation Commission · docket UE-230892 · Order 02 Accepting Puget Sound Energy's 2024-2025 Biennial Conservation Report · Table 1; findings (3)-(4); paragraph 21(1) As the document puts it"PSE overachieved both its EIA target of 304,400 MWh and its EIA Penalty Threshold of 268,702 MWh, achieving 519,873 MWh of EIA Penalty-Liable Achievement"; "PSE is in compliance with its biennial conservation targets accepted in Order 01, WAC 480-109-120, and RCW" 19.285.040; "PSE achieved 235,951 MWh in excess conservation savings that may be used to mitigate shortfalls in the subsequent two biennial targets". Effective 2026-09-10.
Not yet curated Washington Utilities and Transportation Commission · UTC docket search, company Puget Sound Energy, keyword Renewable Portfolio Standard · newest matching docket UE-250401 (2025 Annual Renewable Portfolio Standard Report), closed 2025-08-08, no order listed As the document puts itNo 2026 renewable portfolio standard docket found for PSE on 2026-09-21; Avista (UE-260468) and PacifiCorp (UE-260464) 2025 reports closed 2026-08-13. Commerce's page says that after 2026-06-12 utilities move from annual to biennial EIA reporting (HB 2575). The 15 percent figure in the Commerce summary is a compilation, not a commission finding. Not available: no source
The open proceeding Where the next decision is being made, and how to take part.
PSE's electric biennial conservation plan for 2026-2027: docket pending; the 2026-2027 biennial conservation report will be reviewed hereopen Washington Utilities and Transportation Commission · docket UE-250834 · Docket UE-250834 page (status Pending; filed 2025-10-31; Order 01 of 2026-01-14) · docket page As the document puts itStatus Pending on 2026-09-21 with no scheduled event after Order 01. The 2024-2025 cycle in UE-230892 ran: report filed 2026-06-01, notice of written comments 2026-06-22, staff comments 2026-07-31, Order 02 2026-09-10. No renewable-target (RPS) docket for 2026 was found for PSE.Next: 2026-2027 biennial conservation report and commission review; no date scheduled on the docket page· Take part ↗
SAO says it examines "13 qualifying utilities" for EIA and "39 qualifying utilities" for CETA — the count difference (18 vs 13) is unexplained; cooperatives are audited independently.
open
After June 12, 2026, utilities will shift from annual reporting on EIA compliance progress to biennial reporting.
open
"PSE exceeded its commission-approved target of 3,084,363 megawatt hours … acquiring 3,794,770" (news 2022, snapshot).
open
Commerce's 2026 report summary carries the 2024-2025 conservation target for Puget Sound Energy as 268,702 MWh; the commission's Order 01 in UE-230892 accepted a target of 304,400 MWh and a penalty threshold of 268,702 MWh.
Compiled by Commerce, not a compliance determination
RCW 19.285.040(1) ↗ · Washington State Department of Commerce, EIA 2026 Report Summary and Detail.xlsx, sheet Conservation by Utility · utility reports submitted 2026-06-01 · checked 2026-09-27
Commerce's 2026 Energy Independence Act report summary, from the utilities' reports submitted 2026-06-01. Every value is Commerce's cell; the two percent columns are Commerce's own formulas, shown in Commerce's format and never recomputed. Rows are alphabetical and nothing is ranked. Whether a utility complied is decided by the commission for an investor-owned utility and examined by the State Auditor for a consumer-owned one.
Biennium 2024-2025. Each value is the publisher’s cell at the row and column given; this utility’s row is marked.
Utilitysheet row
TargetMWh · column B
Acquired in 2024MWh · column C
Acquired in 2025MWh · column D
Excess carried from the prior two bienniumsMWh · column E
Total savings, percent of the targetpercent, the publisher’s formula · column F
Acquired, percent of retail loadpercent, the publisher’s formula · column G
Consumer-owned utilities, each against its own targetEach sets its biennial target by action of its governing board (WAC 194-37-070(2) and (4)). A percent compares a utility with its own target, not with another utility's.
Investor-owned utilities, listed apartThe commission accepts these targets (WAC 480-109-120), and Commerce's target column does not use one basis for the three: each row says which figure Commerce printed, beside the commission's order.
Avista ↗row 3 Target column: Avista's total conservation goal: the commission's 63,374 MWh EIA target plus the 3,169 MWh decoupling penalty threshold (UE-230897 Order 01) 2024-2025 biennial conservation acquisition target accepted by the commission: 63,374 MWh · UE-230897 Order ↗2024-2025 EIA penalty threshold accepted by the commission: 47,635 MWh · UE-230897 Order ↗
66,543 MWh
51,580 MWh
45,279 MWh
0 MWh
146%
0.8%
PacifiCorp ↗row 15 Target column: the commission's 2024-2025 EIA target itself (UE-230904 Order 01); its penalty threshold is 74,839 MWh 2024-2025 biennial conservation acquisition target accepted by the commission: 84,971 MWh · UE-230904 Order ↗2024-2025 EIA penalty threshold accepted by the commission: 74,839 MWh · UE-230904 Order ↗
84,971 MWh
40,269 MWh
53,920 MWh
0 MWh
111%
1.2%
Puget Sound Energy this utilityrow 17 Target column: the commission's 2024-2025 EIA penalty threshold (UE-230892 Order 01), not its 304,400 MWh EIA target 2024-2025 biennial conservation acquisition target accepted by the commission: 304,400 MWh · UE-230892 Order ↗2024-2025 EIA penalty threshold accepted by the commission: 268,702 MWh · UE-230892 Order ↗
268,702 MWh
280,964 MWh
293,527 MWh
0 MWh
214%
1.4%
Totalrow 21 · Commerce's own line: its sum of all eighteen rows, the three investor-owned figures on their differing bases included. As printed, never recomputed.
SAIDISystem Average Interruption Duration Index: the minutes of sustained interruption the average customer had over the year, customer-minutes interrupted divided by customers served. Each utility calculates and reports its own figure on EIA-861 Schedule 3, under the method it declares. A system average says nothing about one address.Definition ↗, SAIFISystem Average Interruption Frequency Index: how many sustained interruptions the average customer had over the year, customers interrupted divided by customers served, as the utility reports it on EIA-861 Schedule 3.Definition ↗ and CAIDICustomer Average Interruption Duration Index: minutes per sustained interruption, SAIDI divided by SAIFI on the same basis. EIA-861 asks utilities for SAIDI and SAIFI only; EIA publishes CAIDI with the data and the atlas shows it as published, never recomputed.Definition ↗ count sustained interruptions. Figures with and without major event daysDays a utility sets apart from normal operation: EIA describes them as events such as snowstorms, floods or heatwaves, or periods of outages that differ greatly from the utility's own five-year history. EIA-861 asks for the indices both with and without them. Part B respondents determine them under IEEE 1366; Part C respondents define a major event themselves. The two series answer different questions and are never blended.Definition ↗ are different measures; compare like with like.
WA · IEEE 1366EIA-861 Schedule 3 has two parts. Part B is for utilities that calculate SAIDI and SAIFI and determine major event days under IEEE 1366-2003 or IEEE 1366-2012; Part C is for any other method, where the utility also states how it defines a momentary interruption and whether inactive accounts count as customers. Figures from the two parts are not comparable and the atlas never pools them; utilities under Part C do not share one method either.Definition ↗
Index
Major event days included
Major event days excluded
Included, loss of supply removed
SAIDIminutes/customer/year
1,196
203
1,122
SAIFIinterruptions/customer/year
2.2
1.2
2
CAIDIminutes/interruption
543.6
169.2
561
Customers the indices are based on
1,240,043 customers
Highest voltage counted as distribution
34.5 kV
How it was measuredDetermined under IEEE 1366-2003 or IEEE 1366-2012; the form does not record which edition
Outages recorded automatically: yes
Others reporting the same way · major event days included21 utilities in WA under IEEE 1366. Each counts once whatever its size; this is context, not a ranking.
SAIDI median 258.5 (52.9–1,887) minutes/customer/yearSAIFI median 1.41 interruptions/customer/year
Others reporting the same way · major event days excluded21 utilities in WA under IEEE 1366. Each counts once whatever its size; this is context, not a ranking.
SAIDI median 136.1 (39.5–604.7) minutes/customer/yearSAIFI median 1 interruptions/customer/year
Every year filed
As filed each year. SAIDI in minutes per customer per year; SAIFI in interruptions per customer per year. Blank cells were not reported.
Year
State
Standard
SAIDI with
SAIDI without
SAIFI with
SAIFI without
Customers
2024
WA
IEEE 1366
1,196
203
2.2
1.2
1,240,043
2023
WA
IEEE 1366
203
167
1.3
1.1
1,222,236
2022
WA
IEEE 1366
447
196
1.66
1.09
1,208,346
2021
WA
IEEE 1366
849
207
2.27
1.26
1,192,766
2020
WA
IEEE 1366
414
171
1.7
1.06
1,180,611
2019
WA
IEEE 1366
550
136
1.57
0.96
1,165,638
2018
WA
IEEE 1366
434
145
1.52
0.99
1,148,866
2017
WA
IEEE 1366
477
175
1.8
1.12
1,137,364
2016
WA
IEEE 1366
391
154
1.63
1.02
1,126,181
2015
WA
IEEE 1366
760
161
2.18
1.04
1,114,074
2014
WA
IEEE 1366
540
153
1.84
0.96
1,105,450
2013
WA
IEEE 1366
209
124
1.13
0.86
1,100,259
Reported by the utility on EIA-861 Schedule 3 under the method it declares. IEEE 1366 and other-method figures are not comparable, and values with and without major event days answer different questions. A system average says nothing about one address. CAIDI is published by EIA as SAIDI divided by SAIFI; it is not a line on the form. A value the utility left blank stays blank. Source and licence· Frozen facts for this utility ↗
Customer programmes
EIA-861 Schedule 6, as filed
Programme results as each utility filed them, by customer class and report year, each in its own unit. Classes are never added into a total, years are never added into a period, and savings are never divided by sales. The one ratio shown, enrolled demand-response customers against the utility's own EIA-861 customer count for the same state, class and year, carries both counts.
Energy efficiency EIA-861 Schedule 6 Part A
Reported by the utility on EIA-861 Schedule 6 Part A as adjusted gross savings at the customer meter under its own evaluation; figures are not comparable across utilities. Reporting-year incremental savings are annualized for participants new that year; life-cycle savings run over the programmes' planned life (energy as a lump sum, peak as the average annual reduction). Each class is shown as filed and the total row is the filer's own; nothing is summed here. Costs are nominal dollars of the report year (the form collects thousands; PUDL publishes dollars). A blank stays blank.
Report year 2024, WA. Each row is one customer class as filed; the filer's total is its own line and is not the sum of the rows above. Costs are nominal dollars.
Class
Incremental annual energy savings, reporting year (annualized)MWh
Customer incentives, incremental life-cycle cost (nominal)USD · life cycle
Other costs, incremental life-cycle (nominal)USD · life cycle
Other costs, reporting-year incremental (nominal)USD
CommercialPSEI
138,785 MWh
21.6 MW
1,696,739 MWh
21.6 MW
12.2 years
$48,224,026
$48,224,026
$12,603,563
$12,603,563
IndustrialPSEI
13,170 MWh
1.8 MW
146,268 MWh
1.8 MW
11.1 years
$5,358,225
$5,358,225
$1,400,396
$1,400,396
ResidentialPSEI
106,190 MWh
19.9 MW
1,041,018 MWh
19.9 MW
9.8 years
$42,436,081
$42,436,081
$10,111,132
$10,111,132
TransportationPSEI
not reported
not reported
not reported
not reported
not reported
not reported
not reported
not reported
not reported
Filer's totalPSEI
258,145 MWh
43.3 MW
2,884,025 MWh
43.3 MW
not applicable
$96,018,332
$96,018,332
$24,115,091
$24,115,091
Demand response EIA-861 Schedule 6 Part B
Reported by the utility on EIA-861 Schedule 6 Part B. Potential peak savings assume every programme is called; actual peak savings are what was achieved at the company's own annual peak hour, and the two are never merged. Customers are enrolled customers, a count. Costs are nominal dollars of the report year. The form has no total row and none is computed here. A blank stays blank.
Report year 2024, WA. Each row is one customer class as filed; the form has no total row and none is computed. Costs are nominal dollars.
Class
Customers enrolled in demand response programmescount
Energy savings from demand responseMWh
Potential peak demand savings, all demand response calledMW · potential
Actual peak demand savings at the annual system peak hourMW · achieved
Customer incentives (nominal)USD
Other programme costs (nominal)USD
Enrolled share of this class's customersderived
CommercialPSEI
301
28 MWh
4.1 MW
3.4 MW
$171,000
$401,000
0.2%301 of 143,363
IndustrialPSEI
19
40 MWh
9.2 MW
9.1 MW
$385,000
$899,000
0.6%19 of 3,188
ResidentialPSEI
601,946
1,759 MWh
53 MW
52.9 MW
$3,606,000
$5,178,000
55.1%601,946 of 1,091,599
TransportationPSEI
not reported
not reported
not reported
not reported
not reported
not reported
not reported
Population: organizations of this release with EIA-861 rows in the core states. A short-form respondent has no figures to file; a long-form respondent without a row may have no programmes or may have a nonutility administrator reporting for it. Years without a row are listed against the table's span, not against the years this utility filed the form.
What the sheet says
TariffA utility’s published rates and charges, with an effective date.Definition ↗ · not a bill
Schedule 7· WA· effective 2026-05-01
Basic chargeper month
$7.49
EnergyResidential Service· WA UTC (tariff WN U-60)
0.148363 USD/kWh first 600 kWh; 0.167780 above; plus electric conservation 0.009409, power cost adjustment 0.038719, energy exchange credit -0.006648, other -0.002378
Adjustment schedules named on the sheetlisted, never added in
tier prices bundle schedules 7, 111 (cap-and-invest), 129, 140, the 141 series and 142
Summary of Total Current Prices, Sheet S-1; an 800 kWh example bill on the same sheet is 161.36 USD.Source sheet ↗read 2026-09-18· OpenEI entry ↗ dated 2026-03-21, a discovery index only
ModeledComputed billsA declared usage case priced on a published tariff sheet: kWh in one bill, the days it covers, and where the sheet has them a service size, dwelling type or jurisdiction and a season. The total is the schedule's own charges: the fixed charge plus the energy charge by tier. Where the same sheet prints prices for named adjustments or credits, a second, separately labelled total adds them; those prices change on their own schedules. Whatever the sheet only names, such as a city tax, is listed and never added, so neither total is a complete bill. It is an illustration, not a billing record, and it is not the realized average revenue per kWh that EIA-861 reports.Definition ↗ for 3 declared cases. Prices are the sheet’s own; usage and days are assumptions.
Case
Schedule charges (USD)
With adjustments the sheet prices (USD)
Next kWh costs (USD/kWh)
Average (cents/kWh)
600 kWh over 30 days
$96.51
$119.97
$0.148363$0.187465 with adjustments
16.09schedule charges ÷ kWh
900 kWh over 30 days
$146.84
$182.04
$0.16778$0.206882 with adjustments
16.32schedule charges ÷ kWh
1,200 kWh over 30 days
$197.18
$244.10
$0.16778$0.206882 with adjustments
16.43schedule charges ÷ kWh
How each total adds up
600 kWh over 30 days
Line
Quantity
Price
Amount (USD)
Basic Charge
1 month
$7.4900 per month
$7.49
Electricity Charge0–600 kWh
600 kWh
$0.148363 per kWh
$89.02
Schedule charges
$96.51
Electric Cons. Program Chargeadjustment priced on the sheet
600 kWh
$0.009409 per kWh
$5.65
Power Cost Adjustmentadjustment priced on the sheet
600 kWh
$0.038719 per kWh
$23.23
Energy Exchange Creditadjustment priced on the sheet
600 kWh
$-0.006648 per kWh
$-3.99
Other Electric Charges & Creditsadjustment priced on the sheet
600 kWh
$-0.002378 per kWh
$-1.43
With adjustments the sheet prices
$119.97
900 kWh over 30 days
Line
Quantity
Price
Amount (USD)
Basic Charge
1 month
$7.4900 per month
$7.49
Electricity Charge0–600 kWh
600 kWh
$0.148363 per kWh
$89.02
Electricity Charge600–∞ kWh
300 kWh
$0.16778 per kWh
$50.33
Schedule charges
$146.84
Electric Cons. Program Chargeadjustment priced on the sheet
900 kWh
$0.009409 per kWh
$8.47
Power Cost Adjustmentadjustment priced on the sheet
900 kWh
$0.038719 per kWh
$34.85
Energy Exchange Creditadjustment priced on the sheet
900 kWh
$-0.006648 per kWh
$-5.98
Other Electric Charges & Creditsadjustment priced on the sheet
900 kWh
$-0.002378 per kWh
$-2.14
With adjustments the sheet prices
$182.04
1,200 kWh over 30 days
Line
Quantity
Price
Amount (USD)
Basic Charge
1 month
$7.4900 per month
$7.49
Electricity Charge0–600 kWh
600 kWh
$0.148363 per kWh
$89.02
Electricity Charge600–∞ kWh
600 kWh
$0.16778 per kWh
$100.67
Schedule charges
$197.18
Electric Cons. Program Chargeadjustment priced on the sheet
1,200 kWh
$0.009409 per kWh
$11.29
Power Cost Adjustmentadjustment priced on the sheet
1,200 kWh
$0.038719 per kWh
$46.46
Energy Exchange Creditadjustment priced on the sheet
1,200 kWh
$-0.006648 per kWh
$-7.98
Other Electric Charges & Creditsadjustment priced on the sheet
1,200 kWh
$-0.002378 per kWh
$-2.85
With adjustments the sheet prices
$244.10
Named on the sheet without a price, so in neither total: Effect of city tax.
The utility’s own example on the sheet: 800 kWh over 30 days = $161.36. Computed here with its priced adjustments: $161.36(difference $0.00).
Schedule 150· Net Metering Services for Customer-Generator Systems· effective 2026-01-20
Available to customers on schedules 7, 24, 25 and 29 operating a fuel cell or a hydroelectric, solar or wind generator of no more than 25 kW total capacity; the cost of the programme is collected through the schedule 83 and 150 surcharges
Read from the Summary of Total Current Prices, Sheet S-27; the 25 kW cap is lower than the 100 kW the state statute allows.Source ↗read 2026-09-18
The price on the utility's own sheet on the date it was read, with the adjustment schedules it names listed beside it and never added in. It is not a bill, and it is not the realized average revenue per kWh that EIA-861 reports above: the two answer different questions.
Distributed generationCustomer-sited and small generation reported by utilities in aggregate on EIA-861; no locations; a separate population from the plant inventory, never added to it.Definition ↗
Utility reports · no locations
Distributed generation reported by this utility to EIA-861 for 2024, by state
Utility-reported, no locations, not in the EIA-860 plant inventory (>= 1 MW). Storage is listed separately and never added to generation capacity. Non-net-metered units >= 1 MW can also appear in EIA-860; the overlap is disclosed, not resolved. Source rollup rows are excluded from every sum.
Sum of EIA-861 utility-reported nameplate capacity over leaf technology classes, excluding storage and source rollup rows; utility x state grain; no locations; not part of the EIA-860 plant inventory
2024 calendar year · reported · derived · valid · final
1 of 1 reporting utilities included.
net-metered + non-net-metered; the two EIA-861 schedules are disjoint by design
Customer counts can include the same customer under more than one technology. Energy sold to utilities measures exports; it does not measure all generation at customer sites.
Net-metered customers
25,213count
2024
Source & method
EIA-861 net metering customer count over leaf technology classes; a customer with two technologies can be counted twice by the source
2024 calendar year · reported · derived · valid · final
Washington State Legislature (RCW 19.405, RCW 19.285), Washington Utilities and Transportation Commission orders and docket filings, Washington State Department of Commerce EIA and CEIP report summaries, and each utility's own filings, cited per row
One assertion per row, five kinds kept apart: what applies, what is owed, what the utility filed, what the issuing body decided, and the open proceeding. A fuel-mix value is not a compliance verdict, and a filing that restates a target does not enact it; standing on each row says whose figure it is. An absent row states what was checked and when; a utility not in the file has not been curated.
Display names and aliases (pipeline/config/crosswalks/aliases.csv)
Display names verified against each organization's own website; EIA legal names retained as aliases
A display name is the name an organization uses for itself; the EIA name stays searchable and on the record. Each row cites the page that shows the name.
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Forms 860/923
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Forms 860/923
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Form 861
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Form 861
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Form 861
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Forms 860/923
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)