Klickitat County, WA. Reports to the Bonneville Power Administration balancing authorityThe organization that balances electricity supply and demand in a reporting area.Definition ↗.
Nameplate capacity, operating generatorsFull nameplate rating of the operating generators, before ownership shares. MW measures rated power; annual output is energy in MWh.Definition ↗
Not reported
Source & method
Sum of generator nameplate MW with operational status code OP in the inventory year; one row per generator; unscaled by ownership
2024 inventory · reported · derived · missing · final
0 of 0 operating generators included.
No generator with status OP in this inventory year
Net generationEnergy produced over the stated period after the plant’s own use, including signed storage output. Plant output is not allocated to owners or buyers.Definition ↗
Not reported
2024
Source & method
Sum of EIA-923 annual net generation over the plant's unique prime-mover x energy-source rows; negative values (pumping, station use) retained
2024 calendar year · reported · derived · missing · final
Net generation MWh / (operating nameplate MW x hours in year); only when every operating generator was operating before the year began and none retired during it
2024 calendar year · reported · derived · missing · final
derived: net_generation_mwh@2024 / (nameplate_mw_op x 8784 h)
Ownership basisHow a generator's owners were established: from EIA-860's ownership schedule (reported), from EIA's rule that a unit absent from a complete schedule is wholly owned by its operator (derived), or unknown.Definition ↗
OperatorThe organization that runs a plant. It may have different owners.Definition ↗Not reported
Operating nameplate MW x ownership fraction, once per generator; reported schedule or EIA-860 schedule-4 default. Ownership source & rules ↗
CO2 filed by EPA-monitored units
2024
The EIA-860 inventory for 2024 lists no existing generator at this plant, so there is no unit EPA could monitor. Source
1 historical units with unknown current state
Unit TG1: last assertion July 2016through February 2017 (exclusive), RE, 3.5 MW. Not present in this monthly workbook.
Latest inventoryThe newest complete monthly inventory, with dated status and capacity changes beside the annual baseline totals.Definition ↗ · August 2026
Status unknown
No confirmed status or capacity changes among comparable units. Missing monthly assertions and units outside the baseline have no like-for-like comparison.
Operating nameplate capacity, latest inventoryOperating nameplate MW in this monthly inventory. Compare it with the annual baseline; do not add the two inventories together.Definition ↗
Not reported
· provisional
Source & method
Sum of nameplate MW over generators whose current-valid EIA-860M workbook assertion has status OP; dated by the complete inventory edition; never added to the baseline aggregate
Planned nameplate capacity, latest inventoryNameplate MW proposed or under construction in this monthly inventory, separate from operating MW. Planned dates are forecasts.Definition ↗
Not reported
· provisional
Source & method
Sum of nameplate MW over generators whose current-valid EIA-860M workbook assertion is a proposal or construction stage (P, L, T, U, V, OT, TS); a proposal is not a commitment and its date is a forecast
Retired or cancelled nameplate capacity, latest inventory
10MW
· provisional
Partial or uncertain coverage: Historical units have unknown current state
Source & method
Sum of nameplate MW over generators whose current-valid EIA-860M workbook assertion is retired, cancelled or indefinitely postponed (RE, CN, IP); retired is not demolished
Each unit's operating span from its reported operating date to its retirement date or to the August 2026 inventory (the vertical line). Dashed spans start at a planned operating date, a forecast; a short bar marks a planned retirement. Standby and out-of-service units are hatched.
Units as a table
Unit lifecycle from EIA-860M, August 2026.
Unit
State
Operating since
Planned
Retired
MW
TG2
Retired or cancelled
July 1985
—
December 2021
5MW
TG3
Retired or cancelled
July 2002
—
December 2021
5MW
Independently dated by EIA-860M; the baseline facts above stay the validated edition. Planned dates are forecasts; retired is not demolished.
Approximate service areasAn approximate utility service area. The boundary cannot identify the supplier for a particular address.Definition ↗ containing the plant’s location. A geographic candidate, not a supply relationship.
Within 3 km of the reported plant point, nearest first. BPA’s published lines, HIFLD-compiled lines of other owners and HIFLD 2022 substations; nearness does not establish an electrical connection.
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Forms 860/923
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Forms 860/923
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)
Catalyst Cooperative, PUDL v2026.9.0, derived from U.S. EIA Forms 860/923
Data transformed by PUDL from U.S. EIA forms; selected fields republished; EIA data is public with dated acknowledgment (https://www.eia.gov/about/copyrights_reuse.php)