Micron memory fab (Micron FAB), Boise

Micron Technology, Inc. · contracting as Micron Idaho Semiconductor Manufacturing (Triton) LLC · Boise, ID · semiconductor fab

Exhibit 3 of the ESA (the year-by-year Scheduled Ramp Contract Demand and Minimum Monthly Billing Demand in kW) is printed in the public application but is not transcribed here: the PDF's font encoding defeated text extraction on 2026-09-21, so those figures await a read from the rendered document. The existing Micron Technology campus is a separate ESA customer and is not part of this dossier.

Site
Micron Boise campus, 8000 South Federal WayBuildings: Micron FAB; second Boise fabPhases: expansion (Scheduled Ramp Contract Demand, to 2030-10-01); first fab; second fab; steady state (Embedded Contract Demand, from 2030-10-01)The ESA (Application Attachment 1) names the customer and the site, "a new memory manufacturing fab complex located at 8000 South Federal Way, Boise, Idaho (the 'Micron FAB') that will be served by the CHIP substation at 230:34.5kV"; Idaho Power's 2025 IRP Appendix A lists Micron Idaho Semiconductor Manufacturing as an ESA customer beside Micron Technology's existing campus; Micron's own releases announce the Boise fab.
Served by
Idaho Power Co Named by a filing, not by proximity: docket IPC-E-24-44.
Tariff or contract
Schedule 28Sheet ↗
Dockets

Why this facility: The largest named load with public figures in the region and not a data center: the utility's application states the anticipated steady-state peak, the ESA states the interconnection-facilities size and the minimum-billing floor, and the commission's order fixes the prices. A second Boise fab was announced on 2025-06-12 with no size; it is a separate phase with no row.

Announced

What was announced, in the announcer's own unit: floor or cleanroom area, dollars or a power figure. A press or agency release counts only here.
  • the cleanroom space will reach 600,000 square feet Micron Technology, Inc. · Press release: Micron Breaks Ground on Leading-Edge Manufacturing Fab in Boise, Idaho · paragraph 2· cleanroom area as announced, not building footprint
    600,000 sq ft2022-09-12Source ↗
  • historic $15 billion investment through the end of the decade in Boiserestated later Micron Technology, Inc. · Press release: Micron Breaks Ground on Leading-Edge Manufacturing Fab in Boise, Idaho · dateline BOISE, Idaho, Sept. 12, 2022; paragraphs 1-3· announced investment, nominal dollars
    15,000,000,000 USD2022-09-12Source ↗
  • In 2022, Micron announced plans to construct a $15 billion leading-edge memory manufacturing facility in Boise Idaho Power · 2025 Integrated Resource Plan, Appendix A: Sales and Load Forecast (June 2025) · page 25, Micron Idaho Semiconductor Manufacturing· the utility restating the announced investment; the same figure, not an addition
    15,000,000,000 USD2025-06-01Source ↗
  • an additional $30 billion beyond prior plans which includes building a second leading-edge memory fab in Boise, Idaho, and expanding and modernizing its existing manufacturing facility in Manassas, Virginia Micron Technology, Inc. · Press release: Micron and Trump Administration Announce Expanded U.S. Investments · dateline BOISE, Idaho, June 12, 2025 no source
    No public figure2025-06-12Source ↗

Requested from the utility

What the customer asked the utility to serve, from the utility's filing or the regulator's record; a threshold or floor where the schedule is confidential.
  • Micron anticipates an annual peak demand at steady state of approximately 507 MW, beginning in 2031 Idaho Power · docket IPC-E-24-44 · Application for approval of special contract and tariff Schedule 28 · paragraph 11 (Contract Demand)· anticipated annual peak demand at steady state, the basis of the Embedded Contract Demand; the expansion period's Scheduled Ramp Contract Demand is Exhibit 3 (see facility note)
    507 MW2031Source ↗

Minimum billed whether used or not

The minimum the applicable tariff sheet or executed contract bills whether used or not.
  • Minimum Monthly Billing Demand will automatically reduce by 30 MW on June 1 of each year down to a minimum of 20 MW Idaho Power · docket IPC-E-24-44 · Micron FAB Special Contract section 5.5; Order 37039 · section 5.5(a)-(b); Order 37039 ordering paragraphs (Billing Demand charge $20.25 per kW, Contract Demand charge $3.12 per kW, initial Energy Charge $0.04084 per kWh)· the floor after expansion: on the Embedded Contract Demand's effective date the Minimum Monthly Billing Demand falls 30 MW from the then-effective amount, then 30 MW each June 1 to 20 MW; during expansion it equals the Scheduled Ramp Contract Demand in Exhibit 3
    20 MW2026-05-08Source ↗

Contracted

What an executed agreement makes available or interconnection facilities are built to carry.
  • Micron is paying Idaho Power to construct the necessary Interconnection Facilities to accommodate the Scheduled Ramp Contract Demand for the Micron FAB up to 416,200 kW Idaho Power · docket IPC-E-24-44 · Micron FAB Special Contract (Application Attachment 1) · section 6.1 Additional Facilities· interconnection facilities under the Construction Agreement of 2023-05-16 and the Amended and Restated Procurement Agreement of 2023-02-01; the ESA says these may not be sufficient to supply the maximum Contract Demand of 507 MW
    416,200 kW2024-11-21Source ↗
  • the maximum Contract Demand of 507 MW Idaho Power · docket IPC-E-24-44 · Micron FAB Special Contract (Application Attachment 1) · section 6.1; section 1.6 (Contract Demand definition quoted in Order 37039 footnote 1)· maximum Contract Demand the ESA names; the same 507 MW as the anticipated steady-state peak, in its contractual role, and never added to it
    507 MW2024-11-21Source ↗

Forecast attributed to this facility

A utility's or regulator's forecast attributable to this facility alone, with its vintage and geography.
  • Individual energy and peak-demand forecasts are developed for ESA customers, including Micron Idaho Semiconductor Manufacturing; only the additional-firm-load class total is published Idaho Power · 2025 Integrated Resource Plan, Appendix A: Sales and Load Forecast (June 2025) · page 23 (Additional Firm Load), Table 8 page 24, Appendix A1 page 44 not published: held by Idaho Power: customer-level forecast inside the 2025 IRP, published only as the additional-firm-load class (258 aMW in 2026 rising to 1,065 aMW in 2035) with Brisbie, INL, Lamb Weston, Micron Technology, Simplot and others
    No public figure2025-06-01Source ↗

Measured use

What the meter recorded over a stated period, if any public document states it.
  • Service under Schedule 28 begins the earlier of the first month the aggregate power requirement at the Micron FAB exceeds 20,000 kW or 2026-06-01; metered use is billed by Idaho Power and not published Idaho Power · docket IPC-E-24-44 · Micron FAB Special Contract section 2.1(a); Order 37039 · section 2.1(a) not published: held by Idaho Power (Schedule 28 billing) and Micron Idaho Semiconductor Manufacturing (Triton) LLC; no public filing carries metered kWh or the commencement of service
    No public figure2026-05-08Source ↗

What is not public

  • Forecast attributed to this facilityIndividual energy and peak-demand forecasts are developed for ESA customers, including Micron Idaho Semiconductor Manufacturing; only the additional-firm-load class total is publishedHeld by Idaho Power: customer-level forecast inside the 2025 IRP, published only as the additional-firm-load class (258 aMW in 2026 rising to 1,065 aMW in 2035) with Brisbie, INL, Lamb Weston, Micron Technology, Simplot and others.
    not published2025-06-01· Source ↗
  • Announcedan additional $30 billion beyond prior plans which includes building a second leading-edge memory fab in Boise, Idaho, and expanding and modernizing its existing manufacturing facility in Manassas, Virginia
    no source2025-06-12· Source ↗
  • Measured useService under Schedule 28 begins the earlier of the first month the aggregate power requirement at the Micron FAB exceeds 20,000 kW or 2026-06-01; metered use is billed by Idaho Power and not publishedHeld by Idaho Power (Schedule 28 billing) and Micron Idaho Semiconductor Manufacturing (Triton) LLC; no public filing carries metered kWh or the commencement of service.
    not published2026-05-08· Source ↗

Why nothing here is added up

Never add these figures to each other, to a utility forecast that already includes the facility, or across facilities. The utility on a dossier is the one a filing or contract names. Proximity to a substation, a service-territory polygon or a balancing authority never establishes who serves a facility.

  • A superseded announcement restates the earlier one: the chain is one figure, not several.
  • A service request, a minimum billing demand, a contracted capacity and a metered use describe one facility in different roles; the same MW can appear in more than one.
  • A utility's class forecast (Idaho Power's additional firm load, PGE's data-center load) already contains its named customers: adding a named figure counts it twice.
  • MW, MWa, MWh and square feet are different quantities; dollars are not load.