New 115 kV Creston Substation

Entity project:bpaq:L0619 · release 20260929T050546Z-51ae0f7d3c78 · schema 1.41.0. Immutable citation page; values as published in this release. Current pages may be newer.

FactValueUnitPeriodEvidence / methodQualitySource and locator
Project nameplate capacity as stated9.8MW2026-09-28reported / directvalidbpa-queue
Interconnection Request Queue (generator interconnection and line/load requests), published workbook; request_number=L0619; field=Nameplate MW Total
Maximum summer interconnection service requested10.0MW2026-09-28reported / directvalidbpa-queue
Interconnection Request Queue (generator interconnection and line/load requests), published workbook; request_number=L0619; field=Max Summer Interconnection Service MW